AQC is performed every 8 hours and is considered to be just like ampuled QC.  (which is why IQCP is not needed).
Does anyone not perform ampule QC (external) with every measurement cartridge change? 

Statement from Siemens
This cartridge-based system provides QC material in a standardized and unique manner that removes the need for operator intervention and ensures the running of specific levels of QC at specified time intervals, as regulatory requirements dictate or according to individual hospital protocol. 
It is important to note that cartridge-based AQC is just like ampuled QC, an external form of quality control. It is simply packaged differently and is more convenient. The AQC cartridge is entirely external to the measurement system, and the controls are value-assigned to a master lot by the manufacturer. The consistency of the manufacturing process allows the laboratory to consider their AQC as one long lot number with no expiration date. The elimination of room-air contamination allows the laboratory to consider using the data as one long shift on a day-to-day basis. This technology allows all laboratories to apply the same expected ranges over time for a given type of analyzer.





2 Replies

We do not use external QC, Completes, for new cartridge replacement. All three levels of auto QC are ran after the calibration and before patient testing is allowed, locked out until then. 

We never use anything but the AQC.

Reply
Subgroup Membership is required to post Replies
Join POCT Listserv now
Sylvia Lowery
almost 5 years ago
2
Replies
0
Likes
4
Followers
766
Views
Liked By:
Suggested Posts
TopicRepliesLikesViewsParticipantsLast Reply
Nova Stat Strip
Dimitrinka Yancheff
about 5 hours ago
90247
Melissa Willcox
about 2 hours ago
HemataSTAT II
Karissa Goulder
1 day ago
00154
Karissa Goulder
1 day ago
Lead testing
Anita Belanger
1 day ago
20220
Monica Kaufman
about 5 hours ago