iSTAT users

3 followers
0 Likes

Is there a way to run the scheduled controls a head of time? 

2 Replies

You can run controls as unscheduled but it will not give you credit for doing the scheduled QC.  Your iSTATs will lock out testing even if that QC was acceptable when run as unscheduled.  I don't think the iSTAT will allow you to run the QC before your scheduled time. You can turn off your schedule QC , run the QC then reset your schedule again for your next run. 

No, it won't give you credit for running the QC before the scheduled time.  You can run it but if it's before it's due it will require it when the scheduled due date comes around.  It gives you a grace period after the date but nothing before.

Reply
Subgroup Membership is required to post Replies
Join POCT Listserv now
Ashlee Byquist
about 4 years ago
2
Replies
0
Likes
3
Followers
465
Views
Liked By:
Suggested Posts
TopicRepliesLikesViewsParticipantsLast Reply
TEG6s for Pediatrics
Brittany Behrendt
4 days ago
30199
Kristin Cox
3 days ago
Affinion 2 Dropping Numbers from both Operator ID and Specimen ID When Scanning?
Annie Janssen
4 days ago
20207
Lori Lasbury
4 days ago
NovaPlus HCG Pregnancy Test Cassettes - Back order?
Orlando Dominguez
4 days ago
10197
Mi Hui Scales
4 days ago